Code of Federal Regulations · Section
§ 40.33 — Issuance Of A License For A Uranium Enrichment Facility
10 C.F.R. § 40.33
View:
(a) The Commission will hold a hearing pursuant to 10 CFR part 2, subparts A, G, and I, on each application with regard to the licensing of the construction and operation of a uranium enrichment facility. The Commission will publish public notice of the hearing in the Federal Register at least 30 days before the hearing.
(b) A license for a uranium enrichment facility may not be issued before the hearing is completed and a decision issued on the application.
Authorizing Statute
-
Establishment and transfers42 U.S.C. § 5841
-
Authority and functions of Director44 U.S.C. § 3504
-
License requirements for transfers42 U.S.C. § 2092
-
Acquisition and disposition of lands and materials42 U.S.C. § 7914