(a) DOE shall not receive or possess source, special nuclear, or byproduct material at a geologic repository operations area except as authorized by a license issued by the Commission pursuant to this part.
(b) DOE shall not commence construction of a geologic repository operations area unless it has filed an application with the Commission and has obtained construction authorization as provided in this part. Failure to comply with this requirement shall be grounds for denial of a license.
Authorizing Statute
-
Storage or disposal facility planning42 U.S.C. § 2021a
-
Authority and functions of Director44 U.S.C. § 3504
-
Site approval and construction authorization42 U.S.C. § 10134
-