Code of Federal Regulations · Section
§ 851.41 — Settlement
10 C.F.R. § 851.41
(a) DOE encourages settlement of a proceeding under this subpart at any time if the settlement is consistent with this part. The Enforcement Director and a contractor may confer at any time concerning settlement. A settlement conference is not open to the public and DOE does not make a transcript of the conference.
(b) Notwithstanding any other provision of this part, the Enforcement Director may resolve any issues in an outstanding proceeding under this subpart with a consent order.
(1) The Enforcement Director and the contractor, or a duly authorized representative thereto, must sign the consent order and indicate agreement to the terms contained therein.
(2) A contractor is not required to admit in a consent order that a requirement of this part has been violated.
(3) DOE is not required to make a finding in a consent order that a contractor has violated a requirement of this part.
(4) A consent order must set forth the relevant facts that form the basis for the order and what remedy, if any, is imposed.
(5) A consent order shall constitute a final order.
Authorizing Statute
-
Congressional declaration of policy and purpose42 U.S.C. § 5801
-
Establishment and mission50 U.S.C. § 2401
-
General duties of Commission42 U.S.C. § 2201
-
Mode of recovery28 U.S.C. § 2461
-
Definitions42 U.S.C. § 7101