§ 16.17 — Procedures Upon Congressional Authorization Of Takeover

18 C.F.R. § 16.17

View:

If Congress authorizes the takeover of a hydroelectric power project as provided under section 14 of the Federal Power Act:

(a) The Commission or the Director of the Office of Energy Projects will notify the existing licensee in writing of the authorization at least two years before the takeover occurs; and

(b) The licensee must present any claim for compensation to the Commission:

(1) Within six months of issuance of the notice of takeover; and

(2) As provided in section 14 of the Federal Power Act.