§ 1000.1440 — What Constitutes A “significant Change” In The Original Scope Of Work?
25 C.F.R. § 1000.1440
View:
A significant change in the original scope of work is:
(a) A change that would result in a cost that exceeds the total of the Federal project funds available and the Tribe's/Consortium's contingency funds; or
(b) A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.