Code of Federal Regulations · Section
§ 203.90 — What Is In A Fabricator's Confirmation Report?
30 C.F.R. § 203.90
View:
This report shows you have committed in a timely way to the approved system for production. This report must include the following (or its equivalent for unconventionally acquired systems):
(a) A copy of the contract(s) under which the fabrication yard is building the approved system for you;
(b) A letter from the contractor building the system to the BSEE Regional Director for your region certifying when construction started on your system; and
(c) Evidence of an appropriate down payment or equal action that you've started acquiring the approved system.
Authorizing Statute
-
Definitions30 U.S.C. § 351
-
Definitions30 U.S.C. § 1001
-
Leases of unallotted lands for mining purposes; duration of leases25 U.S.C. § 396a
-
Definitions43 U.S.C. § 1301
-
Fees and charges for Government services and things of value31 U.S.C. § 9701
-
Congressional statement of findings and purposes30 U.S.C. § 1701
-
Leases of allotted lands for mining purposes25 U.S.C. § 396
-
Definitions25 U.S.C. § 2101
-
Definitions43 U.S.C. § 1331
-
Congressional findings43 U.S.C. § 1801