Code of Federal Regulations · Section
§ 285.912 — After I Remove A Facility, Cable, Or Pipeline, What Information Must I Submit?
30 C.F.R. § 285.912
View:
Within 60 days after you remove a facility, cable, or pipeline, you must submit a written report to BSEE that includes the following:
(a) A summary of the removal activities, including the date they were completed;
(b) A description of any mitigation measures you took; and
(c) If you used explosives, a statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the facility were consistent with those in the approved decommissioning application.
Authorizing Statute
-
Definitions43 U.S.C. § 1331