§ 585.652 — How Long Do I Have To Conduct Activities Under An Approved Gap?
30 C.F.R. § 585.652
View:
After BOEM approves your GAP, you have:
(a) For a limited lease, the time period established under § 585.236(a)(2), unless we renew the operations period under §§ 585.425 through 585.429.
(b) For a ROW grant or RUE grant, the time provided in the terms of the grant.