Code of Federal Regulations · Section
§ 75.219 — Exceptions To The Procedures Under § 75.217
34 C.F.R. § 75.219
View:
The Secretary may select an application for funding without following the procedures in § 75.217 if:
(a) The objectives of the project cannot be achieved unless the Secretary makes the grant before the date grants can be made under the procedures in § 75.217;
(b) (1) The application was submitted under the program's preceding competition;
(2) The application was not selected for funding because the application was mishandled or improperly processed by the Department; and
(3) The application has been rated highly enough to deserve selection under § 75.217; or
(c) The Secretary receives an unsolicited application that meets the requirements of § 75.222.
Authorizing Statute
-
Family educational and privacy rights20 U.S.C. § 1232g