§ 60.1215 — What Emission Limits Must I Meet? By When?
40 C.F.R. § 60.1215
View:
You must meet the emission limits specified in tables 1 and 2 of this subpart. You must meet the limits 60 days after your municipal waste combustion unit reaches the maximum load level but no later than 180 days after its initial startup.