Code of Federal Regulations · Section
§ 60.2952 — What Must I Submit Prior To Commencing Construction?
40 C.F.R. § 60.2952
View:
You must submit a notification prior to commencing construction that includes the five items listed in paragraphs (a) through (e) of this section.
(a) A statement of intent to construct.
(b) The anticipated date of commencement of construction.
(c) All documentation produced as a result of the siting requirements of § 60.2895.
(d) The waste management plan as specified in §§ 60.2899 through 60.2901.
(e) Anticipated date of initial startup.
Authorizing Statute
-
Congressional findings and declaration of purpose42 U.S.C. § 7401