Code of Federal Regulations · Section
§ 3276.13 — What Additional Information Must I Give Blm In The Monthly Report For Flash And Dry Steam Facilities?
43 C.F.R. § 3276.13
View:
In addition to the regular monthly report information required by § 3276.12, send to BLM:
(a) Steam flow into the turbine in klbs; for dual flash facilities, you must separate the steam flow into high pressure steam and low pressure steam;
(b) Condenser pressure in psia;
(c) Condenser temperature in deg. F;
(d) Auxiliary steam flow used for gas ejectors, steam seals, pumps, etc., in klbs;
(e) Flow of condensate out of the plant (after the cooling towers) in klbs; and
(f) Any other information we may require.
Authorizing Statute
-
Congressional declaration of policy43 U.S.C. § 1701