Code of Federal Regulations · Section

§ 3282.3 — When Must The Unit Operator Submit An Application For Blm Approval Of A Proposed Initial Participating Area?

43 C.F.R. § 3282.3

View:

The unit operator must submit an application for BLM approval of a proposed participating area no later than:

(a) 60 days after receiving BLM's determination identified in § 3281.15(a)(3) that a unit well will produce or utilize in commercial quantities; or

(b) 30 days before the initiation of commercial operations, whichever occurs earlier.

Authorizing Statute