§ 4300.23 — After I File My Application, Can I Use The Land Before Blm Issues My Permit?
43 C.F.R. § 4300.23
View:
No. You cannot use the land until BLM issues you a permit. Generally, BLM will issue a permit within 120 days after receiving an application and will keep you informed if there are delays in meeting that timeframe.