§ 2553.107 — What Must A Sponsor Do If It Cannot Meet Its Performance Measures?

45 C.F.R. § 2553.107

View:

When a sponsor finds it is not on track to meet its performance measures, the sponsor must develop a plan to get back on track or submit a request to AmeriCorps to amend its performance measures. AmeriCorps may limit when amendments to performance measure can be submitted, as well as limit the types of changes a sponsor can make to performance measures. The request must include all of the following:

(a) Why the project is not on track to meet its performance requirements;

(b) How the project has been tracking performance measures;

(c) Evidence of corrective steps taken;

(d) Any new proposed performance measures; and

(e) A plan to ensure that the project will meet the new proposed measure(s).