Code of Federal Regulations · Section
§ 154.460 — Design Criteria
46 C.F.R. § 154.460
At static angles of heel up through 30°, a secondary barrier must
(a) If a complete secondary barrier is required in § 154.459, hold all of the liquid cargo in the cargo tank for at least 15 days under the dynamic loads in § 154.409(e);
(b) If a partial secondary barrier is permitted in § 154.459, hold any leakage of liquid cargo corresponding to the extent of failure under § 154.448(a) after initial detection or primary barrier leak for at least 15 days under the dynamic loads in § 154.409(e);
(c) If the primary barrier fails, prevent the temperature of the vessel's structure from falling below the minimum allowable service temperature of the steel; and
(d) Be designed so that a cargo tank failure does not cause a failure in the secondary barrier.
Authorizing Statute
-
Regulations46 U.S.C. § 3703