Code of Federal Regulations · Section
§ 32.110 — 32.110 Payment Of Subcontractors Under Cost-reimbursement Prime Contracts
48 C.F.R. § 32.110
If the contractor makes financing payments to a subcontractor under a cost-reimbursement prime contract, the contracting officer should accept the financing payments as reimbursable costs of the prime contract only under the following conditions:
(a) The payments are made under the criteria in subpart 32.5 for customary progress payments based on costs, 32.202-1 for commercial product or commercial service purchase financing, or 32.1003 for performance-based payments, as applicable.
(b) If customary progress payments are made, the payments do not exceed the progress payment rate in 32.501-1, unless unusual progress payments to the subcontractor have been approved in accordance with 32.501-2.
(c) If customary progress payments are made, the subcontractor complies with the liquidation principles of 32.503-8, 32.503-9, and 32.503-10.
(d) If performance-based payments are made, the subcontractor complies with the liquidation principles of 32.1004(d).
(e) The subcontract contains financing payments terms as prescribed in this part.
Authorizing Statute
-
Chapter 137 legacy provisions10 U.S.C. § 3016
-
Administrative40 U.S.C. § 121
-
General authority41 U.S.C. § 1121
-
Powers of the Administration in performance of functions51 U.S.C. § 20113