§ 42.1305 — 42.1305 Contract Clauses
48 C.F.R. § 42.1305
(a) The contracting officer shall insert the clause at 52.242-14, Suspension of Work, in solicitations and contracts when a fixed-price construction or architect-engineer contract is contemplated.
(b) (1) The contracting officer may, when contracting by negotiation, insert the clause at 52.242-15, Stop-Work Order, in solicitations and contracts for supplies, services, or research and development.
(2) If a cost-reimbursement contract is contemplated, the contracting officer shall use the clause with its Alternate I.
(c) The contracting officer shall insert the clause at 52.242-17, Government Delay of Work, in solicitations and contracts when a fixed-price contract is contemplated for supplies other than commercial or modified-commercial products. The clause use is optional when a fixed-price contract is contemplated for services, or for supplies that are commercial or modified-commercial products.
Authorizing Statute
-
Administrative40 U.S.C. § 121
-
Chapter 137 legacy provisions10 U.S.C. § 3016
-
General authority41 U.S.C. § 1121
-
Powers of the Administration in performance of functions51 U.S.C. § 20113