§ 52.242-2 — 52.242-2 Production Progress Reports

48 C.F.R. § 52.242-2

View:

As prescribed in 42.1107(a), insert the following clause;

(a) The Contractor shall prepare and submit to the Contracting Officer the production progress reports specified in the contract Schedule.

(b) During any delay in furnishing a production progress report required under this contract, the Contracting Officer may withhold from payment an amount not exceeding $25,000 or 5 percent of the amount of this contract, whichever is less.