Code of Federal Regulations · Section
§ 852.235-73 — 852.235-73 Facilities
48 C.F.R. § 852.235-73
View:
As prescribed at 835.003-74, insert the following clause:
(a) The facilities specified in the contract are considered essential to the work being performed under this contract. Therefore, prior to removing, replacing, or diverting any of the listed or specified facilities, the Contractor shall—
(1) Notify the Contracting Officer in writing; and
(2) Submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the potential impact on this contract.
(b) The Contractor shall make no removal, replacement or diversion of facilities without the Contracting Officer's written consent.
(End of clause)
Authorizing Statute
-
Chief Acquisition Officers and senior procurement executives41 U.S.C. § 1702
-
Functions and authority41 U.S.C. § 1303
-
Administrative40 U.S.C. § 121
-
General authority41 U.S.C. § 1121