Code of Federal Regulations · Section
§ 191.9 — Distribution System: Incident Report
49 C.F.R. § 191.9
View:
(a) Except as provided in paragraph (c) of this section, each operator of a distribution pipeline system shall submit Department of Transportation Form PHMSA F 7100.1 as soon as practicable but not more than 30 days after detection of an incident required to be reported under § 191.5.
(b) When additional relevant information is obtained after the report is submitted under paragraph (a) of this section, the operator shall make supplementary reports as deemed necessary with a clear reference by date and subject to the original report.
(c) Master meter operators are not required to submit an incident report as required by this section.
Authorizing Statute
-
Administrative49 U.S.C. § 5121
-
Rights-of-way for pipelines through Federal lands30 U.S.C. § 185