Code of Federal Regulations · Section
§ 633.23 — Fta Review Of A Project Management Plan
49 C.F.R. § 633.23
View:
Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:
(a) The plan is approved;
(b) The plan is disapproved, including the reasons for the disapproval;
(c) The plan will require modification, as specified, before approval; or
(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.
Authorizing Statute
-
Project management oversight49 U.S.C. § 5327
-
Administrative provisions49 U.S.C. § 5334