Code of Federal Regulations · Section
§ 75.519-1 — -1 Main Power Circuits; Disconnecting Switches; Locations
30 C.F.R. § 75.519-1
View:
Section 75.519 requires (a) that a disconnecting switch be installed on the surface at a point within 500 feet of the place where the main power circuit enters the underground area of a mine, and (b) that, in an instance on which a main power circuit enters the underground area through a shaft or borehole, a disconnecting switch be installed underground within 500 feet of the bottom of the shaft or borehole.
Authorizing Statute
-
Mandatory safety and health standards30 U.S.C. § 811