Within 60 days after you permanently plug a well or remove a platform or other facility, you must verify that the site is clear of obstructions by using one of the following methods:
(a) For a well site, you must either:
(1) Drag a trawl over the site;
(2) Scan across the location using sonar equipment;
(3) Inspect the site using a diver;
(4) Videotape the site using a camera on a remotely operated vehicle (ROV); or
(5) Use another method approved by the District Manager if the particular site conditions warrant.
(b) For a platform or other facility site in water depths less than 300 feet, you must drag a trawl over the site.
(c) For a platform or other facility site in water depths 300 feet or more, you must either:
(1) Drag a trawl over the site;
(2) Scan across the site using sonar equipment; or
(3) Use another method approved by the Regional Supervisor if the particular site conditions warrant.
Authorizing Statute
-
Fees and charges for Government services and things of value31 U.S.C. § 9701
-
Secretarial authority30 U.S.C. § 1751
-
Oil and hazardous substance liability33 U.S.C. § 1321
-
Administration of leasing43 U.S.C. § 1334