Code of Federal Regulations · Subpart
Subpart Q — Decommissioning Activities
30 C.F.R. pt. 250, subpt. Q
- § 250.1700 What Do The Terms “decommissioning,” “obstructions,” “facility,” And “predecessor” Mean In This Subpart?
- § 250.1701 Who Must Meet The Decommissioning Obligations In This Subpart?
- § 250.1702 When Do I Accrue Decommissioning Obligations?
- § 250.1703 What Are The General Requirements For Decommissioning?
- § 250.1704 What Decommissioning Applications And Reports Must I Submit And When Must I Submit Them?
- § 250.1708 How Will Bsee Enforce Accrued Decommissioning Obligations Against Predecessors?
- § 250.1709 [reserved]
- § 250.1710 When Must I Permanently Plug All Wells On A Lease?
- § 250.1711 When Will Bsee Order Me To Permanently Plug A Well?
- § 250.1712 What Information Must I Submit Before I Permanently Plug A Well Or Zone?
- § 250.1713 [reserved]
- § 250.1714 What Must I Accomplish With Well Plugs?
- § 250.1715 How Must I Permanently Plug A Well?
- § 250.1716 To What Depth Must I Remove Wellheads And Casings?
- § 250.1717 [reserved]
- § 250.1721 If I Temporarily Abandon A Well That I Plan To Re-enter, What Must I Do?
- § 250.1722 If I Install A Subsea Protective Device, What Requirements Must I Meet?
- § 250.1723 What Must I Do When It Is No Longer Necessary To Maintain A Well In Temporary Abandoned Status?
- § 250.1725 When Do I Have To Remove Platforms And Other Facilities?
- § 250.1726 When Must I Submit An Initial Platform Removal Application And What Must It Include?
- § 250.1727 What Information Must I Include In My Final Application To Remove A Platform Or Other Facility?
- § 250.1728 To What Depth Must I Remove A Platform Or Other Facility?
- § 250.1729 After I Remove A Platform Or Other Facility, What Information Must I Submit?
- § 250.1730 When Might Bsee Approve Partial Structure Removal Or Toppling In Place?
- § 250.1731 Who Is Responsible For Decommissioning An Ocs Facility Subject To An Alternate Use Rue?
- § 250.1740 How Must I Verify That The Site Of A Permanently Plugged Well, Removed Platform, Or Other Removed Facility Is Clear Of Obstructions?
- § 250.1741 If I Drag A Trawl Across A Site, What Requirements Must I Meet?
- § 250.1742 What Other Methods Can I Use To Verify That A Site Is Clear?
- § 250.1743 How Do I Certify That A Site Is Clear Of Obstructions?
- § 250.1750 When May I Decommission A Pipeline In Place?
- § 250.1751 How Do I Decommission A Pipeline In Place?
- § 250.1752 How Do I Remove A Pipeline?
- § 250.1753 After I Decommission A Pipeline, What Information Must I Submit?
- § 250.1754 When Must I Remove A Pipeline Decommissioned In Place?
- § 250.1705-250.1707 §§ 250.1705-250.1707 [reserved]