(a) For a well site, you must submit to the appropriate District Manager within 30 days after you complete the verification activities a form BSEE-0124, Application for Permit to Modify, to include the following information:
(1) A signed certification that the well site area is cleared of all obstructions;
(2) The date the verification work was performed and the vessel used;
(3) The extent of the area surveyed;
(4) The survey method used;
(5) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(6) A post-trawling job plot or map showing the trawled area.
(b) For a platform or other facility site, you must submit the following information to the appropriate Regional Supervisor within 30 days after you complete the verification activities:
(1) A letter signed by an authorized company official certifying that the platform or other facility site area is cleared of all obstructions and that a company representative witnessed the verification activities;
(2) A letter signed by an authorized official of the company that performed the verification work for you certifying that it cleared the platform or other facility site area of all obstructions;
(3) The date the verification work was performed and the vessel used;
(4) The extent of the area surveyed;
(5) The survey method used;
(6) The results of the survey, including a list of any debris removed or a statement from the trawling contractor that no objects were recovered; and
(7) A post-trawling job plot or map showing the trawled area.
Authorizing Statute
-
Fees and charges for Government services and things of value31 U.S.C. § 9701
-
Secretarial authority30 U.S.C. § 1751
-
Oil and hazardous substance liability33 U.S.C. § 1321
-
Administration of leasing43 U.S.C. § 1334